Current Projects

Pioneer 2 Ward

Owner: LDS Church

Architect: BHD

Contract Amount: $3,965,928

Percent complete: 75

Fremont Ward

Owner: LDS Church

Architect: Bott Pantone

Contract Amount: $4,204,539

Percent Complete: 90

Smith Family Park

Owner: Farr West City

Contract Amount: $188,692

Percent Complete: 95

Evanston Stake

Owner: LDS Church

Architect: ea architecture

Contract Amount: $4,969,999

Percent Complete: 15


WSU Institute

Owner: LDS Church

Architect: Bott Pantone

Contract Amount

Percent Complete: 34


Wellington Church

Owner: LDS Church

Architect: Bott Pantone

Contract amount:

Percent complete: 100

IHC WTC 19th Floor

Owner:

Architect: AGC Architecture

Contract Amount: $1,014,978

Percent Complete: 51

OWATC Restrooms

 Owner: State of Utah

Architect:

Contract Amount: $466,256

Percent Complete: 100

Davis ATC Restroom Remodels

 Owner: State of Utah
Architect: Design West
Contract Amount: $399,174
Percent Complete: 90

Recently Completed Projects

N. Ogden Jr. High Gym Addition

Owner: Weber School District

Architect: Bott Pantone

Contract Amount:$5,478,204

Completion date: May 2017

Coalville 1,2 seismic

Owner: LDS Church 

Architect: 

Contract Amount: $1,682,980 

Completion Date: 

IHC Cancer Center

Owner: IHC

Architect: VCBO

Contract Amount: $1,348,660

Completion Date: Feb. 2018


DaVinci Academy

Owner: DaVinci Academy
Architect:
Contract Amount: $90,307.95
Completion Date: Dec. 2017

Sandy City Elevator

 Owner: Sandy City
Architect:
Contract Amount: $157,867
Completion Date: June 2017

Saunders Dental

Owner: Richard Saunders, Ryan Saunders

Architect:

Contract Amount $425,390

Completion Date: Oct. 2015

Jacobs Ranch Church

Owner: LDS Church
Architect: EA Architecture
Contract Amount: $3,990,000
Completion Date: Dec. 2016

IHC Wound Care

Owner: IHC

Architect: NJRA

Contract Amount: $406,000

Completion Date: Nov. 2016

Select Health VCT 1st Floor

Owner: IHC Health Services
Architect: VCBO
Contract Amount:$638,790
Completion Date:

Deaf & Blind School Playground

 Owner: State of Utah
Architect: Landmark Design
Contract Amount:$319,931
Completion Date:

Box Elder Academy Kitchen

Owner: Brigham City Corp.
Architect: FFKR
Contract Amount:$652,314
Completion Date: Dec. 2015

Box Elder Academy Center

Owner: Brigham City Corp.
Architect: FFKR
Contract Amount: $3,181,660
Completion Date: Dec. 2015

IHC Lake Park

 Owner: IHC Health Services
Architect: VCBO
Contract Amount: $4,129,595
Completion Date: 

Bountiful 4,20 Boiler Replacement

Owner: LDS Church
Architect: Abercrombie, Jensen & Assoc.
Contract Amount: $370,000
Completion Date: Oct. 2015

Eagle Mountain Church Roof

 Owner: LDS Church
Architect: McNeil Engineering
Contract Amount: $314,932
Completion Date:

LDS Simulation Center

 Owner: IHC Health Services
Architect: VCBO
Contract Amount: $1,272,227
Completion Date:

Simple Stories Remodel

 Owner:
Architect: GSBS
Contract Amount:$323,005.15
Completion Date: Feb. 2015

Clearfield Arts Center

 Owner:  
Architect: CEC Engineering
Contract Amount: $151,000
Completion Date: May 2015

Davis Behavioral Health

Owner: Davis County

Architect: Dixon & Associates

Contract Amount: $2,446,758.12

Completion Date: September 2011